03/07/2006
More delays for Wembley Stadium
The completion of the new Wembley Stadium looks likely to be delayed even further, the construction firm working on the project has announced.
Australian firm Multiplex said that it did not expect that construction work on the £757 million stadium would be finished until after September.
In a statement, Multiplex claimed that "certain works" that were the responsibility of Wembley National Stadium LTD had not yet been carried out. The statement said: "In order to achieve practical completion of Wembley Stadium certain works, which are the responsibility of WNSL, rather than Multiplex must first be completed; WNSL has not begun some of these works."
The statement added: "Furthermore, once practical completion has been achieved, it is the responsibility of WNSL to carry out a series of critical works and activities in order to make the stadium operational for events.
"The timing and hosting of the first event is therefore entirely a matter for WNSL."
However, a statement released by Wembley Stadium's chief executive Michael Cunnah, said: "Wembley Stadium firmly rejects Multiplex's statement and refutes any claims that they make against us. The delays experienced on the stadium have and continue to be under the complete control and responsibility of the Multiplex. Although the stadium appears to be nearly finished, Multiplex has an important and substantial amount of work to complete, including the installation, testing and commissioning of mechanical and electrical systems.
"Wembley Stadium took the sensible decision in March to rule out all events at the stadium in 2006 as we were sceptical of Multiplex ability to meet the various deadlines they have given us. The situation remains the same - Multiplex need to make more progress in delivering the stadium before we can name an opening date."
The new stadium had been due to host its first event - the 2006 FA Cup final - in May, but the Football Association announced in March that no events would be held at the venue this year because of the delays.
Once building work has been completed, WNSL has said that it will need two months to hold 'test events' at the stadium for safety reasons before a major event can be held there.
(KMcA)
Australian firm Multiplex said that it did not expect that construction work on the £757 million stadium would be finished until after September.
In a statement, Multiplex claimed that "certain works" that were the responsibility of Wembley National Stadium LTD had not yet been carried out. The statement said: "In order to achieve practical completion of Wembley Stadium certain works, which are the responsibility of WNSL, rather than Multiplex must first be completed; WNSL has not begun some of these works."
The statement added: "Furthermore, once practical completion has been achieved, it is the responsibility of WNSL to carry out a series of critical works and activities in order to make the stadium operational for events.
"The timing and hosting of the first event is therefore entirely a matter for WNSL."
However, a statement released by Wembley Stadium's chief executive Michael Cunnah, said: "Wembley Stadium firmly rejects Multiplex's statement and refutes any claims that they make against us. The delays experienced on the stadium have and continue to be under the complete control and responsibility of the Multiplex. Although the stadium appears to be nearly finished, Multiplex has an important and substantial amount of work to complete, including the installation, testing and commissioning of mechanical and electrical systems.
"Wembley Stadium took the sensible decision in March to rule out all events at the stadium in 2006 as we were sceptical of Multiplex ability to meet the various deadlines they have given us. The situation remains the same - Multiplex need to make more progress in delivering the stadium before we can name an opening date."
The new stadium had been due to host its first event - the 2006 FA Cup final - in May, but the Football Association announced in March that no events would be held at the venue this year because of the delays.
Once building work has been completed, WNSL has said that it will need two months to hold 'test events' at the stadium for safety reasons before a major event can be held there.
(KMcA)
Related UK National News Stories
Click here for the latest headlines.
18 August 2005
Wembley stadium still on target, builders claim
The Australian firm working on the construction of Wembley Stadium have insisted that it will be ready in time for the FA Cup Final in May, next year. However, Multiplex have said that they are revising their profit forecast for 2006 to 215 million Australian dollars from an earlier forecast of between A$220 - A$235 million.
Wembley stadium still on target, builders claim
The Australian firm working on the construction of Wembley Stadium have insisted that it will be ready in time for the FA Cup Final in May, next year. However, Multiplex have said that they are revising their profit forecast for 2006 to 215 million Australian dollars from an earlier forecast of between A$220 - A$235 million.
21 February 2006
Wembley misses deadline for FA Cup final
The new Wembley Stadium will not be ready for the FA Cup final in May, the Football Association has announced.
Wembley misses deadline for FA Cup final
The new Wembley Stadium will not be ready for the FA Cup final in May, the Football Association has announced.
01 August 2006
Wembley Stadium 'unlikely to open until June 2007'
The opening of the new Wembley Stadium looks set to be delayed until June 2007. The venue had been due to be completed by August 2005, but construction has been hit by a series of delays, which resulted in this year's FA Cup Final being moved to the Millennium Stadium in Cardiff.
Wembley Stadium 'unlikely to open until June 2007'
The opening of the new Wembley Stadium looks set to be delayed until June 2007. The venue had been due to be completed by August 2005, but construction has been hit by a series of delays, which resulted in this year's FA Cup Final being moved to the Millennium Stadium in Cardiff.
16 November 2011
Guilty Plea For Wembley Killing
A man has pleaded guilty to the fatal assault of another man outside Wembley Stadium in September. Ian Mytton, 41, of Gateley Close, Redditch, Worcestershire, appeared at the Old Bailey on Wednesday, charged with manslaughter of 44-year-old Michael Dye outside Wembley Stadium on September 6.
Guilty Plea For Wembley Killing
A man has pleaded guilty to the fatal assault of another man outside Wembley Stadium in September. Ian Mytton, 41, of Gateley Close, Redditch, Worcestershire, appeared at the Old Bailey on Wednesday, charged with manslaughter of 44-year-old Michael Dye outside Wembley Stadium on September 6.
02 May 2013
Olympic Stadium To Host RWC Games
London's Olympic Stadium will host five games at the 2015 Rugby World Cup. Twickenham will host the opening match of the event on 18 September, with England facing the winner of the Oceania qualifying competition.
Olympic Stadium To Host RWC Games
London's Olympic Stadium will host five games at the 2015 Rugby World Cup. Twickenham will host the opening match of the event on 18 September, with England facing the winner of the Oceania qualifying competition.
-
Northern Ireland WeatherToday:After a dry start this morning rain will spread from the northwest across all parts. This afternoon will be dull with some patchy rain and drizzle. Becoming much milder through the afternoon. Maximum temperature 11 °C.Tonight:A cloudy evening and night with a little light rain or drizzle, perhaps some clear periods developing along the east coast. A very mild night everywhere. Minimum temperature 10 °C.