24/03/2009
Cross-Border Energy Supply In Jeopardy
An electricity interconnector project across the Irish border has been revealed to be about nine months behind schedule.
It has also been estimated to be costing around £1.5 million more than first envisaged. However, Northern Ireland electricity users could be under threat as early as 2014 if the long-awaited interconnector with the Republic of Ireland isn't built.
Iain Osborne, Chief Executive, of the Northern Ireland Authority for Energy Regulation warned that the existing grid's capacity to distribute extra power will suffer if a 'bottleneck' between north and south isn't speedily resolved.
Mr Osborne told Stormont's Environment Committee: "The social costs of not having enough power are enormous."
The warning comes as a new report, commissioned by NIE and Eirgrid, found that an overhead line would be easier to repair and far cheaper than the underground cable alternative.
However, residents in counties Tyrone and Armagh have been campaigning against plans for an overhead cable from the Republic amid health concerns about its proximity to their homes.
Opponents to the proposed system - planned between Tyrone and Cavan - said the report grossly overestimated the cost of an underground system.
Amid calls for an inquiry, Iain Osborne warned that a lengthy planning process is likely to cost an extra €30m (£22m) in expenses incurred because the existing system isn't fully adequate.
Mr Osborne said: "It is a lot of money if you have a public inquiry, it could be one of the most expensive public inquiries that we have ever ran and I think it is very important that everybody realises it.
"By 2014 we will start to have concerns about security of supply."
It is hoped that an all-island electricity market will bring reduced bills for both domestic and business users through greater competition.
(BMcC/JM)
It has also been estimated to be costing around £1.5 million more than first envisaged. However, Northern Ireland electricity users could be under threat as early as 2014 if the long-awaited interconnector with the Republic of Ireland isn't built.
Iain Osborne, Chief Executive, of the Northern Ireland Authority for Energy Regulation warned that the existing grid's capacity to distribute extra power will suffer if a 'bottleneck' between north and south isn't speedily resolved.
Mr Osborne told Stormont's Environment Committee: "The social costs of not having enough power are enormous."
The warning comes as a new report, commissioned by NIE and Eirgrid, found that an overhead line would be easier to repair and far cheaper than the underground cable alternative.
However, residents in counties Tyrone and Armagh have been campaigning against plans for an overhead cable from the Republic amid health concerns about its proximity to their homes.
Opponents to the proposed system - planned between Tyrone and Cavan - said the report grossly overestimated the cost of an underground system.
Amid calls for an inquiry, Iain Osborne warned that a lengthy planning process is likely to cost an extra €30m (£22m) in expenses incurred because the existing system isn't fully adequate.
Mr Osborne said: "It is a lot of money if you have a public inquiry, it could be one of the most expensive public inquiries that we have ever ran and I think it is very important that everybody realises it.
"By 2014 we will start to have concerns about security of supply."
It is hoped that an all-island electricity market will bring reduced bills for both domestic and business users through greater competition.
(BMcC/JM)
Related Northern Ireland News Stories
Click here for the latest headlines.
03 October 2007
Tobermore To Create 100 Jobs In Derry
County Derry based concrete products manufacturer Tobermore has announced it is to create 100 new jobs as it embarks on an expansion costing £10 million. Tobermore will build a new factory to accommodate for the increases in staff and production.
Tobermore To Create 100 Jobs In Derry
County Derry based concrete products manufacturer Tobermore has announced it is to create 100 new jobs as it embarks on an expansion costing £10 million. Tobermore will build a new factory to accommodate for the increases in staff and production.
04 March 2022
Planning Issues Cost Jobs And Livelihoods
Delays and problems in NI's planning system are costing jobs and livelihoods, Chair of the Assembly's Infrastructure Committee Jonathan Buckley has said.
Planning Issues Cost Jobs And Livelihoods
Delays and problems in NI's planning system are costing jobs and livelihoods, Chair of the Assembly's Infrastructure Committee Jonathan Buckley has said.
24 July 2002
Altnagelvin Hospital gets further medical boost
Altnagelvin Hospital has received another boost following its recent upgrade pledge when Minister for Health, Social Services and Public Safety, Bairbre de Brún, launched a new Magnetic Resonance Imaging (MRI) service at the hospital.
Altnagelvin Hospital gets further medical boost
Altnagelvin Hospital has received another boost following its recent upgrade pledge when Minister for Health, Social Services and Public Safety, Bairbre de Brún, launched a new Magnetic Resonance Imaging (MRI) service at the hospital.
05 December 2013
Osborne Releases Autumn Statement
The government says it is "supporting aspiration" and "helping with the cost of living" in Northern Ireland through measures being announced in George Osborne's Autumn Statement. Measures include the cancellation of a planned fuel duty rise and a transferable tax allowance will benefit married couples.
Osborne Releases Autumn Statement
The government says it is "supporting aspiration" and "helping with the cost of living" in Northern Ireland through measures being announced in George Osborne's Autumn Statement. Measures include the cancellation of a planned fuel duty rise and a transferable tax allowance will benefit married couples.
02 November 2001
Human Organs Inquiry set to answer public’s questions
The Human Organs Inquiry set up by the Department of Health has invited members of the public to come and air their views and listen to health service staff as well as relatives affected by the retention of human organs in Northern Ireland.
Human Organs Inquiry set to answer public’s questions
The Human Organs Inquiry set up by the Department of Health has invited members of the public to come and air their views and listen to health service staff as well as relatives affected by the retention of human organs in Northern Ireland.
-
Northern Ireland WeatherToday:A cloudy day with a little light rain or drizzle at times, but some spells of drier weather too. The north coast may become somewhat brighter later this afternoon. Maximum temperature 11 °C.Tonight:Cloudy and patchy light rain will slowly clear away this evening. Then the rest of the night will be dry with broken cloud. Westerly winds freshening in the early hours. Minimum temperature 6 °C.