25/08/2010
Shock 'Underspend' On School Buildings
Despite claims of a lack of cash from the NI Department of Education (DE), more than £350m set aside for school buildings has not been used.
A Government spending watchdog, the Audit Office said Stormont's Department of Education had "consistently underspent its capital budget".
In the last five years, over £1.2bn was allocated to the department but total expenditure was only £857m.
To make matters worse, the Auditor General Kieran Donnelly said that even with hold-ups in planning, land purchase and legal challenges, school building work should be speeded up.
The damning report also said some school buildings' potential for community use was "not being exploited".
The news follows an investigation into the design quality of school buildings and the DE's strategic planning and management of the school estate and the fact that many schools in Northern Ireland are not fit for purpose because of years of underinvestment.
The Northern Ireland Audit Office added that half of the estate is not ideally suited to deliver the new curriculum and many buildings need costly repairs.
There is a £292m maintenance backlog - equivalent to £900 per pupil.
The probe by Comptroller and Auditor General Kieran Donnelly - School Design And Delivery - also identified significant problems with the general quality of the schools estate and the planning process for the delivery of the capital building programme.
It noted that DE and the education authorities were taking steps to reduce temporary accommodation but there were still nearly 3,000 temporary units in use.
It also showed that improvements to the schools estate were being hampered by delays in delivering projects, with most current schemes expected to take at least six years to complete from when they were originally announced and confirmed that spending was £353m below budget.
Also thrown up was the fact that there was too many extra school places in the system, with surplus capacity estimated at 54,000 places and that community use was not being fully exploited for the schools' estate property.
In the case of construction, barriers to the delivery of schemes include legal issues around site acquisition, waiting for approval from other statutory agencies like the
Planning Service, reviews of long-term pupil enrolments and a legal challenge to the DE's Construction Framework.
However, the delayed establishment of the Education and Skills Authority (ESA) presented a significant opportunity to address many of the issues raised as, in the projects which were being delivered there was clear evidence of improvements in design quality.
The report said: "There is a pressing need to progress the capital investment programme in order to improve the schools estate and enable the effective delivery of the curriculum."
It added: "Improvements to the schools estate, while previously constrained by a lack of resources, are now being constrained by delays in delivering projects."
See: NI Schools Building Plan List Revealed
(BMcC/GK)
A Government spending watchdog, the Audit Office said Stormont's Department of Education had "consistently underspent its capital budget".
In the last five years, over £1.2bn was allocated to the department but total expenditure was only £857m.
To make matters worse, the Auditor General Kieran Donnelly said that even with hold-ups in planning, land purchase and legal challenges, school building work should be speeded up.
The damning report also said some school buildings' potential for community use was "not being exploited".
The news follows an investigation into the design quality of school buildings and the DE's strategic planning and management of the school estate and the fact that many schools in Northern Ireland are not fit for purpose because of years of underinvestment.
The Northern Ireland Audit Office added that half of the estate is not ideally suited to deliver the new curriculum and many buildings need costly repairs.
There is a £292m maintenance backlog - equivalent to £900 per pupil.
The probe by Comptroller and Auditor General Kieran Donnelly - School Design And Delivery - also identified significant problems with the general quality of the schools estate and the planning process for the delivery of the capital building programme.
It noted that DE and the education authorities were taking steps to reduce temporary accommodation but there were still nearly 3,000 temporary units in use.
It also showed that improvements to the schools estate were being hampered by delays in delivering projects, with most current schemes expected to take at least six years to complete from when they were originally announced and confirmed that spending was £353m below budget.
Also thrown up was the fact that there was too many extra school places in the system, with surplus capacity estimated at 54,000 places and that community use was not being fully exploited for the schools' estate property.
In the case of construction, barriers to the delivery of schemes include legal issues around site acquisition, waiting for approval from other statutory agencies like the
Planning Service, reviews of long-term pupil enrolments and a legal challenge to the DE's Construction Framework.
However, the delayed establishment of the Education and Skills Authority (ESA) presented a significant opportunity to address many of the issues raised as, in the projects which were being delivered there was clear evidence of improvements in design quality.
The report said: "There is a pressing need to progress the capital investment programme in order to improve the schools estate and enable the effective delivery of the curriculum."
It added: "Improvements to the schools estate, while previously constrained by a lack of resources, are now being constrained by delays in delivering projects."
See: NI Schools Building Plan List Revealed
(BMcC/GK)
Related Northern Ireland Business News Stories
Click here for the latest headlines.
20 January 2006
Optimum Real Estate 'move in' on NI estate agencies
An internet-based estate agency for Northern Ireland homeowners is currently offering flat-rate fees, promising savings for people selling their home.
Optimum Real Estate 'move in' on NI estate agencies
An internet-based estate agency for Northern Ireland homeowners is currently offering flat-rate fees, promising savings for people selling their home.
13 September 2010
Tánaiste Opens Newly Refurbished School
Tánaiste and Minister for Education and Skills Mary Coughlan has opened the newly refurbished St. Joseph's National School, East Wall, Dublin 3. The school building was refurbished at a cost of €1.1million and funded by the Department of Education and Skillls.
Tánaiste Opens Newly Refurbished School
Tánaiste and Minister for Education and Skills Mary Coughlan has opened the newly refurbished St. Joseph's National School, East Wall, Dublin 3. The school building was refurbished at a cost of €1.1million and funded by the Department of Education and Skillls.
07 September 2005
Optimum Real Estate rolled out across NI
Optimum Real Estate, which was successfully launched in North Down last month, is now being rolled out across Northern Ireland and beyond. The firm offers an alternative to conventional estate agents, operating through its own web site and allowing vendors to sell their homes commission-free.
Optimum Real Estate rolled out across NI
Optimum Real Estate, which was successfully launched in North Down last month, is now being rolled out across Northern Ireland and beyond. The firm offers an alternative to conventional estate agents, operating through its own web site and allowing vendors to sell their homes commission-free.
22 July 2010
PADs Speeds Up Special School Scheme
Robin Newton, East Belfast DUP MLA , has welcomed the good news regarding Tor Bank Special School and its new build programme. Robin Newton said the Planning Service had turned around plans for Tor Bank Special schools in the Dundonald area in just four and a half months due to the Pre Applications Discussions (PADs) process.
PADs Speeds Up Special School Scheme
Robin Newton, East Belfast DUP MLA , has welcomed the good news regarding Tor Bank Special School and its new build programme. Robin Newton said the Planning Service had turned around plans for Tor Bank Special schools in the Dundonald area in just four and a half months due to the Pre Applications Discussions (PADs) process.
08 October 2010
Derry's St Mary's Celebrates Opening
The Stormont Education Minister, Caitríona Ruane, has officially opened the newly built St Mary's College, Londonderry. She officiated at the opening of the new school along with Bishop Hegarty and three generations of St Mary's pupils.
Derry's St Mary's Celebrates Opening
The Stormont Education Minister, Caitríona Ruane, has officially opened the newly built St Mary's College, Londonderry. She officiated at the opening of the new school along with Bishop Hegarty and three generations of St Mary's pupils.