28/06/2010
Sprucefield Bridge 'Ahead Of Schedule'
Good weather has helped deliver better news on the roads this week with a speedy completion of the first part of a major motorway bridge maintenance contract.
Now, work on Phase II at Sprucefield Bridge, Lisburn, is ready to begin on 3 July after Phase I was finished three weeks ahead of schedule.
These works on the country bound side of the M1 motorway are expected to be completed by 21 July 2010 dependent on good weather conditions. This follows the completion of works on the Belfast bound side of the Bridge.
Mark McPeak, Roads Service's Project Manager, said: "Sprucefield Bridge was built in 1966 and requires essential maintenance to ensure it is kept in good condition to continue to cope with today's traffic volumes.
"The contractor has made good progress on the scheme which was helped by the favourable weather in completing the bridge repairs.
"It is now necessary to carry out similar work during Phase II on the other side of the bridge in the country bound direction."
He continued: "The works operations and revised traffic management arrangements have again been carefully programmed to minimise inconvenience to the travelling public, local residents and businesses.
"Despite carrying out the scheme during the July holiday period, disruption will be unavoidable," he continued.
"Country bound traffic will be restricted to one lane through the road works and one dedicated lane to Sprucefield off-slip for A1 traffic. The works are likely to result in delays during peak periods in this direction, and would ask motorists to be patient as these essential works progress."
Phase II temporary traffic management will involve restrictions country bound only. All Belfast bound temporary traffic management has been removed and there will no longer be a requirement to close Sprucefield on-slip, which will help avoid traffic disruption during the morning peak times.
During the works, A1 bound traffic will be required to use Lane 1 and exit the M1 at Junction 7, Sprucefield. All traffic travelling country bound on the M1 will be required to use Lane 2 only. A temporary speed limit will also be in place.
(NS/BMcC)
Now, work on Phase II at Sprucefield Bridge, Lisburn, is ready to begin on 3 July after Phase I was finished three weeks ahead of schedule.
These works on the country bound side of the M1 motorway are expected to be completed by 21 July 2010 dependent on good weather conditions. This follows the completion of works on the Belfast bound side of the Bridge.
Mark McPeak, Roads Service's Project Manager, said: "Sprucefield Bridge was built in 1966 and requires essential maintenance to ensure it is kept in good condition to continue to cope with today's traffic volumes.
"The contractor has made good progress on the scheme which was helped by the favourable weather in completing the bridge repairs.
"It is now necessary to carry out similar work during Phase II on the other side of the bridge in the country bound direction."
He continued: "The works operations and revised traffic management arrangements have again been carefully programmed to minimise inconvenience to the travelling public, local residents and businesses.
"Despite carrying out the scheme during the July holiday period, disruption will be unavoidable," he continued.
"Country bound traffic will be restricted to one lane through the road works and one dedicated lane to Sprucefield off-slip for A1 traffic. The works are likely to result in delays during peak periods in this direction, and would ask motorists to be patient as these essential works progress."
Phase II temporary traffic management will involve restrictions country bound only. All Belfast bound temporary traffic management has been removed and there will no longer be a requirement to close Sprucefield on-slip, which will help avoid traffic disruption during the morning peak times.
During the works, A1 bound traffic will be required to use Lane 1 and exit the M1 at Junction 7, Sprucefield. All traffic travelling country bound on the M1 will be required to use Lane 2 only. A temporary speed limit will also be in place.
(NS/BMcC)
Related Northern Ireland News Stories
Click here for the latest headlines.
09 November 2017
New Traffic Measures Introduced In Belfast
New traffic measures have been introduced on the Antrim Road in Belfast. A new tidal urban clearway arrangement will begin to operate from Monday 13 November. The clearway will operate on the Antrim Road, from its junction with Cliftonville Road to the M2 overbridge, just south of Glengormley.
New Traffic Measures Introduced In Belfast
New traffic measures have been introduced on the Antrim Road in Belfast. A new tidal urban clearway arrangement will begin to operate from Monday 13 November. The clearway will operate on the Antrim Road, from its junction with Cliftonville Road to the M2 overbridge, just south of Glengormley.
03 March 2017
M1 Collision Causes Traffic Delays In Belfast
A crash on the M1, which occurred at about 8am this morning and closed two lanes, has now been cleared. The collision happened on the inside lane of the M1 between Stockmans Lane and Broadway. There have been no reports of any injuries. Two lanes of the motorway were closed and caused significant traffic delays across the city.
M1 Collision Causes Traffic Delays In Belfast
A crash on the M1, which occurred at about 8am this morning and closed two lanes, has now been cleared. The collision happened on the inside lane of the M1 between Stockmans Lane and Broadway. There have been no reports of any injuries. Two lanes of the motorway were closed and caused significant traffic delays across the city.
08 December 2009
Newry Flyover Junction Opens
Just in time for the predicted cross-border shopping invasion, a new flyover junction at Cloghogue, on the A1 Newry bypass, has been officially opened.
Newry Flyover Junction Opens
Just in time for the predicted cross-border shopping invasion, a new flyover junction at Cloghogue, on the A1 Newry bypass, has been officially opened.
21 December 2007
Crash Boy Critical
A road accident in Co Armagh has left a six-year-old boy in a critical condition. The boy suffered head injuries and two men and a woman have also been badly hurt, although their injuries are not thought to be life threatening. The crash, involving two cars, happened on the Red Lion Road in Loughgall on Thursday night.
Crash Boy Critical
A road accident in Co Armagh has left a six-year-old boy in a critical condition. The boy suffered head injuries and two men and a woman have also been badly hurt, although their injuries are not thought to be life threatening. The crash, involving two cars, happened on the Red Lion Road in Loughgall on Thursday night.
18 August 2011
£1m Queen's Bridge Investment Underway
Over £1m in investment work is scheduled to start next week on the Queen Elizabeth II Bridge. NI Transport Minister Danny Kennedy announced that work will start on a £1.3m investment to repair and strengthen the Belfast bridge on Monday 22 August.
£1m Queen's Bridge Investment Underway
Over £1m in investment work is scheduled to start next week on the Queen Elizabeth II Bridge. NI Transport Minister Danny Kennedy announced that work will start on a £1.3m investment to repair and strengthen the Belfast bridge on Monday 22 August.